Selwyn District Council - Business Zone Planning Rules
The below guidance is our knowledge of the rules and regulations and is provided to assist you in your assessment and early planning but does not constitute official or legal advice.
When building an Industrial or Commercial building within a Business Zone in the Selwyn District there are some key rules to follow to make sure you comply with to avoid requiring a Resource Consent.
Selwyn District has 7 main zones within the Business Zone umbrella, all with varying rules.
Areas of Business 1 Zone may also be in “Key Activity Centres” (identified in Appendices 29A/B) which have their own specific requirements to be classed as a permitted activity.
To help you understand the requirements in each zone we have broken down the key permitted activities and rules below for each different zone.
Note: There are area specific rules that may also apply to your project, the XL Structural Architectural Team are available for guidance in the rules of the District Plan.
Permitted Activities
Business 1, 1A, 1B, 2 and 2A Zones:
Any activity which complies with all of the provisions of rules relating to permitted activities.
Business 2B Zone:
Business 3 Zone:
If your business falls within these activities, it will likely be a permitted activity with Council.
If your business operates outside of these categories you will likely require resource consent to build in this zone and the Selwyn District Plan does have specific non-complying activities listed for particular zones, if you are unsure the XL Structural Architectural team will be able to help you confirm.
Maximum Height of proposed buildings
Zone |
Building |
Structure |
Business 1 Zone (except where listed separately below) |
10 metres |
25 metres |
Rolleston Business 1 Zone - Precincts 1 and 8, as identified in Appendix 29A |
15 metres |
25 metres |
Rolleston Business 1 Zone - Precincts 2, 3, 4 and 7, as identified in Appendix 29A |
10 metres |
25 metres |
Lincoln Business 1 Zone - Precinct 1 (Core Retail), as identified in Appendix 29B |
12 metres |
25 metres |
Business 1 Zone in Prebbleton (except Lots 1 and 2 DP 17591 and Lot 1 DP 13679) |
8 metres (plus roof allowance) |
25 metres |
Business 1 Zone at Prebbleton - Lots 1 and 2, DP 17591 and Lot 1 DP13579 |
10 metres (plus roof allowance) |
25 metres |
Business 1A Zone |
8 metres |
20 metres |
Business 2 Zone |
15 metres |
25 metres |
Business 2A and 2B Zone |
15 metres |
25 metres |
Business 3 Zone |
30 metres |
30 metres |
Site Coverage
Recession Planes
There are recession planes specific to individual sites to adhere to if your site adjoins a Residential Zone, the XL Structural Architectural Team will be able to help you confirm.
Setbacks from Boundaries
Other rules applicable to ALL industrial zones in Selwyn District
HAIL and contaminated land
From experience XL is aware a lot of industrial land may have been developed on contaminated or HAIL land. The Selwyn District Plan has rules and policies in place for contaminated land.
XL Structural will be able to assist you with your project to ensure you are not breaching these requirements.
Carparking and Landscaping
The Selwyn District Plan has rules and policies in place for the various Zones for car parking and landscaping. If providing car parking, you will still need to comply with NZS 4121:2001 and provide 1 accessible car park per 1-20 spaces.
It is also important to consider the surrounding environment and where your staff working within your new building will park if limited spaces are provided.
There are also minimum dimensions for car parks depending on the layout you choose to use on your site, along with turning circle and road width requirements. XL can work through the best car park layout for your site with you.
Landscaping requirements differ for each zone with regard to depth, spacing and species of planting.
The Selwyn District Plan also has further rules for Small Scale Commercial Developments designated as LESS THAN 450 sq. metres and Large-Scale Commercial Developments as 450 sq. or more.
These are the main rules which your building needs to comply with to avoid needing a resource consent, it is important to understand there may be further rules to comply with. Selwyn District Plan can be challenging to navigate, we would recommend reaching out to the XL Structural team who will be happy to conduct a concise and detailed preliminary planning review for your project.
You can find the full Selwyn District Plan here